Floods, insecurity slow USD1.3bn MTN project

TELECOMS

|
Image: Flooding in Kogi state. By Nigerian Government
Flooding in Kogi state

By Kokumo Goodie, Lagos, Nigeria

The massive network modernisation and swap-out exercise being implemented by MTN Nigeria, the country's largest mobile operator, as a part of its USD1.3bn 2012 total capital expenditure (capex), is being challenged by the flood disaster and the increasing wave of insecurity in some parts of the country.

Akinwale Goodluck, the telco's Corporate Services Executive, disclosed this during a media interaction in Lagos to update its subscribers on the ongoing project

Goodluck, who appealed for patience on the part of the over 44 million MTN subscribers and other stakeholders, who have been experiencing service hitches on the MTN network, said the various activities related to MTN network moderrnisation were progressing steadily.

"We regret, however, that the pace of work has been considerably challenged by the spate of insecurity coupled with the unprecedented flooding being experienced in many parts of the country," he said.

The network optimisation exercise will affect over 4, 000 base stations of over 10, 000 across the country.

According to Goodluck: "The task that we are undertaking is tantamount to building a new network. We are seeking to replicate what we achieved over a six period in nine months."

Goodluck explained that considerable progress has been recorded with regard to the ongoing network improvement plans, stressing that several swap-outs have reached very advanced stages of completion.

"The entire network modernisation process is a very logistic-intensive one and the problem of insincerity has seriously affected the pace of work in some parts of the country," he said.

Goodluck noted that in at least 13 states, flooding has created additional logistic impediments, resulting in the slowing down of the pace of the ongoing network modernisation efforts.

While acknowledging that MTN's customers had been experiencing some disruptions over the last few weeks, Goodluck said: "We sincerely express our thanks to our customers for their patience," pledging that as much as possible, MTN would stick to its original plan of carrying out the network procedures only at night, with a view to minimising disruptions to services.

He also assured that MTN was doing everything possible, including doubling its work teams, to finalise the project as quickly as possible, even as he pointed out that, because of the current challenges the exercise may have to conclude by first quarter of 2013.

The project, which began in July, 2012, was expected to cover the entire country and was originally expected to span a period of nine months.

"It is a massive investment we are making to boost not only the quality of telephone services, but also to enhance the back-end information and communication technology support which we provide for banking and financial services, the oil industry and several other industries across Nigeria," Goodluck said.



Share the News

Get Daily Newsletter

comments powered by Disqus

MORE TELECOMS NEWS

Huawei seeks to help build better connected Africa

Huawei is seeking closer cooperation with the governments of Zimbabwe and other southern African countries in accelerating connectivity, the company’s VP for Eastern and Southern Africa, has told the Innovation Africa Digital (IAD) Summit 2015 in Vitoria Falls. Read More

NATCOM set to take over NITEL/Mtel assets

The government of Nigeria has cleared the coast for the take-over of the assets of former state-run NITEL and its mobile arm Mtel, by an indigenous firm, NATCOM Consortium. Read More

Nigeria lawmakers approve NCC’s N60.2b budget

Nigeria’s lower legislative chamber, the House of Representatives, has passed the N60.258 billion 2015 budget of the Nigerian Communications Commission (NCC). Read More

Microsoft empowers loyal customers in it Make It Happen Promo

Winners of the Make it Happen Competition have received their prizes at the posh Silver Bird Lounge in Accra.  Read More

Nigeria’s active telephone numbers up to 142m

The Nigerian Communications Commission (NCC) says the number of active telephone lines in the country increased to 142,589,775 in February. Read More

Tigo opens 46th Customer Experience Centre

Tigo Ghana has opened a new Customer Experience Centre in Abeka Lapaz, as part of the company’s ongoing nationwide retail expansion. Read More

TEDx Accra hosts Vodafone Chief Marketing guru Agnes Essah

One of Ghana’s most innovative and inspirational sharing platforms, TEDx Accra, hosted Vodafone Ghana’s Chief Marketing Officer, Agnes Emefa Essah, among other distinguished speakers at this year’s TEDx Accra summit. Read More

NATCOM completes payment in NITEL, Mtel acquisition

The preferred bidder of Nigerian Telecommunications Limited (NITEL) and its mobile arm (Mtel), NATCOM Consortium, has paid $176,575,700 (N29,696,469,600) — being the outstanding 70 per cent of the $252,521,000 bid price for the acquisition of the assets and business units of the enterprises. Read More

Telecom Namibia ends CDMA services

Telecom Namibia has discontinued both the Switch voice and 3G-EvDO data services on its legacy CDMA (Code Division Multiple Access) network.  Read More

World telecom regulators to meet in Libreville in June

A total of 130 telecommunication regulators out of the 193 member states of the International Telecommunication Union (ITU) will meet in the Gabonese capital in June. Read More

PRESS OFFICES

Sage ERP AfricaSAP AfricaSage Pastel AccountingTrust PayVMWareSamsung ElectronicsMitsumi DistributionPhoenix DistributionMTN BusinessSchneider ElectricMultichoiceMicrosoft 4Afrika

FEATURED STORY

e-commerce space untapped, says phonekings heade-commerce space untapped, says phonekings head

E-commerce is the future, says the head of a new online electronics mall launched in Nigeria. Tayo Olusanya spoke to Kokumo Goodie in Lagos.

IN DEPTH

Villagers get solar training at Barefoot College Villagers get solar training at Barefoot College

The Botswana Human Resource Development Council (HRDC) has seconded seven semi-illiterate mostly Ngwatle villagers for a six month solar electrification training course at the famed Barefoot College in India.